Judge blasts planning authorities for lack of enforcement action against mining firm despite 'repeated breaches'

A High Court judge has dismissed a legal bid to instigate planning enforcement action against a mining operator, but has expressed "grave concern" over the lack of enforcement action by planning authorities against the firm despite its "repeated breaches of planning control".

The mine at Cavanacaw (pic: Gordon Dunn, Geograph)
The mine at Cavanacaw (pic: Gordon Dunn, Geograph)

Mr Justice Humphreys was highly critical of the Northern Irish planning authorities' apparent reliance on complaints from the public before deciding whether or not to take enforcement action against Omagh Minerals Limited.

The company, a subsidiary of a major Canadian mining concern, was in 1995 granted planning consent to extract gold, silver and other minerals from an open cast pit at Cavanacaw, Omagh.

A further planning permission was granted in 2015, enabling underground mining and associated surface works, subject to various conditions.

One of those conditions was that a neighbouring 21-hectare blanket bog would be kept free from works associated with the mine and fenced off to protect its flora and fauna.

Local campaigner, William Donnelly, unsuccessfully challenged the 2015 planning permission through the Northern Irish courts.

Omagh Minerals had sunk exploration boreholes without planning permission in 2012, but that position was regularised by a retrospective grant of permission in 2016.

In November 2018, Donnelly wrote to Fermanagh and Omagh District Council complaining that more boreholes had been drilled into the bog in breach of the 2015 planning condition.

The council at first said it was satisfied that no unauthorised works had been carried out on the blanket bog, the High Court in Northern Ireland heard.

And only in March this year did it accept that two boreholes had been sunk in the area of the blanket bog, in clear breach of the 2015 condition.

The council nevertheless decided not to take enforcement action against Omagh Minerals. It cited the passage of time - the boreholes had been drilled in 2015 - and the absence of any evidence of physical damage to the bog.

Donnelly mounted a judicial review challenge to that decision, arguing that, unless some enforcement action were taken, "Omagh Minerals would continue to flout the law and breach the conditions attached to its planning permission".

Rejecting his case, Mr Justice Humphreys said the council enjoyed a wide discretion as to whether to instigate enforcement action against the company.

He told the court: "It must be recognised that the law affords a margin of appreciation, or latitude, to the decision-maker.

"I am satisfied in this case that the council took into account all material considerations and that the decision not to pursue enforcement action was a proportionate one in all the circumstances.

"Mr Donnelly has not adduced any evidence that the boreholes in question have caused any physical damage to the blanket bog.

"Given that the unlawful drilling took place over four years ago, and has not occurred since, and the lack of any physical damage to be remedied, it is difficult to see what purpose an enforcement notice would serve."

However, the judge went on to say: 'It should be a matter of grave public concern that the mining works at this site have been characterised by repeated breaches of planning control which have resulted in no enforcement action taken by the relevant authorities."

There had, he said, been "unauthorised removal of ore from the site in the late 1990s which constituted unlawful EIA development".

According to the court judgment, between 2008 and 2009, half a million tonnes of rock was unlawfully removed from the site and a government ombudsman later found "that the failure to take enforcement action had completely failed to protect the public interest".

Mr Justice Humphreys added: "It is now apparent, almost five years after it occurred, that Omagh Minerals Limited was guilty of a further breach of planning control which did not result in any timely enforcement action.

"It would seem, despite a well-known history of flouting planning requirements, first the department and now the council rely on complaints being raised by members of the public before considering whether or not to take enforcement action."

He concluded: "The court is not satisfied that an approach which relies upon complaints from the public, and evidence produced by them, could properly be seen as compliant" with the planning authorities' legal obligations.

In the Matter of an Application by William Donelly for Leave to Apply for Judicial Review. Case Number: HUM11243


Have you registered with us yet?

Register now to enjoy more articles and free email bulletins

Sign up now
Already registered?
Sign in

Join the conversation with PlanningResource on social media

Follow Us:
Planning Jobs